On-Going Projects

The Electricity Company of Ghana Limited wishes to inform the General Public that our Offices are Open from 8am to 5pm, Mondays to Fridays and our Customer Service Centers are Open from 9am to 2pm on Saturdays, and 1pm to 5pm on Sundays. Thank you. Always at your service.

On-Going Projects

 

 

IMPROVE CUSTOMER SERVICE DELIVERY
1

Provision of Power Supply to the new Achimota Shopping Mall.

2

Provision of a second dedicated 33kV circuit to Sentuo Steel Ltd. in Tema & a dedicated 11kV circuit to the Tigo head office in Accra.

3 Provision of a dedicated 11kV circuits to SSNIT Emporium & Icon House at Airport City as well as other feeders to support the public network
4

Extension of power supply to switchback park development Project & another to SBC Beverages Ghana Ltd

5

Low Voltage and Primary Distribution Network Improvement Projects of the Ashanti Region- Town Hall, Airport 1, Feeder C21, Feeder C31 Station A GBC and WAHW.

6

Low Voltage Network Improvement Projects in the Manhyia and Asokwa District of Ashanti East Region

7

Low Voltage Network Improvement Projects in Konongo District – Odumasi SSNIT area.

8

Low Voltage Network Improvement Projects in Effiduase District - Asotwe, Woraso, Adan Womase, Bonwire, Abira, Serwaa Akura and Ejisu.

9

System Improvement at Oshiokpo

10

Extension of supply to New Seprepor (Phase II)

11

System Improvement & expansion at Koluedor

12

Extension of supply to Kpone Hanaa opposite Kokompe

13

System Improvement at Mlitsakpo North

14

System Improvement & expansion at Bowiri Anyinase

15

RSIP works at Aflao Teshie

16

Rehabilitation of LV network at Tsikpota

17

Extension of supply to Aboadze – Sekondi

18

Upgrade of LV OHL network at Akoon-Tarkwa

19

Extension of Supply to Sokode Ando

20

Rehabilitation of the Primary Substation at Bekwai

21

Construction of a 25km 2x40MVA Tower line from Kuntunase to Bekwai

22

Construction of 11kV & 33kV Offloading Circuits from the Reconstructed Abosso Primary Substation

23

Construction of a Primary Substation at Tema, along the Meridian road

24

Construction of permanent substation at the existing Kpone Industrial area (OLAM) in Tema

25

Provision of a dedicated 11kv underground circuit to the Kumasi shopping mall facility at Asokwa, Kumasi

26 Karpowership Evacuation Project; Conversion of 11kV Overhead Line to underground around Valco, Tema
27 Separation of the Tetteh Quarshie Hospital from the Mampong Township Feeder

 

IMPROVE OPERATIONAL EFFICIENCY
1

Construction of the La Trade-Fair Primary Substation.

2

Secondary Automation Project Phase III and IV.

3

Creation of 11kV offloading circuits from the proposed Shiashie Primary substation in Accra.

4

Creation of 11kV offloading circuits from the 33/11kV substation at Inchaban waterworks.

5

Creation of three (3) 11kV offloading circuits from the newly constructed Aburi Substation.

6

Creation of 11kV offloading circuits from the lotteries primary substation in Accra

7

Expansion of Primary SCADA (Ghana 2)

8

Expansion of the SCADA Project in Accra and Tema (GH3)

9

Secondary SCADA Automation III & IV

  • Greater Accra Region: Tema, Ada
  • Central Region: Cape-Coast, Winneba and Saltpond.
  • Western Region: Takoradi, Bogoso, Esiama.
  • Eastern: Koforidua, Nkawkaw, Somanya, Dwenase.
  • Volta: Ho, Kpando, Nkwanta.
10

Construction of an Indoor Primary Substation at LA-Trade Fair

11

Construction of 33/11kV 2x20/26MVA Kisseman Indoor Primary Substation

12

Creation of 11kV offloading circuits from the 33/11kV substation at Inchaban waterworks

13

Creation of three (3No.) 11kV offloading circuits from the newly constructed Aburi Substation

14

Supply and Installation of complete SCADA System and Network Upgrade Projects in Central Region

15

Construction of an Indoor Primary Substation at Mataheko, and a Switching Station at Agona Nkwanta

16

Weldy Lamont Project

17

China Water & Electric Corporation (CWE Phase 3)

18 Network Extension and Installation of Customer Services in Tema Region (STONE ELECTRICALS) ECG/SEWL-2014/01
19

Network Extension and Installation of Customer Services in Tema and Accra West Region (STONE ELECTRICALS) ECG/SEWL/USP-2014/02

20

Network Extension and Installation of Customer Services in Accra West Region (RENOWNED ELECTRICALS) ECG/SEL-2014/02

21

Network Extension and Installation of Customer Services in Accra West Region (KOMFATHER ELECTRICALS) ECG/KECL/USP-2014/02

22

Network Extension and Installation of Customer Services in Eastern Region (KOMFATHER ELECTRICALS) ECG/KECL/USP-2014/01

23

Network Extension and Installation of Customer Services in the Accra East Region (BOYKA ENGINEERING) ECG/BEL/USP-2015/01

24

Network Extension and Installation of Customer Services in the Eastern Region (VOLTA POWERS ELECTRICAL) ECG/VPECL/USP – 2015/01

 

REDUCE SYSTEM LOSSES
1

Conversion of the Ejisu (Akyeakrom) 33kV outdoor switching station to a 33/11kV substation.

2

Creation of a new 11kV line from the Nsawam substation to relieve the Nsawam- Accra11kV line.

3

LV network improvement at Nmai Djor in Accra East Region

4

No. On-Going RSIP Projects:

5

Rehabilitation of the electricity distribution network within the Tema Community One (1) Market, Tema South District

6 Rehabilitation of the electricity distribution networks within Takoradi Market Circle

 

IMPROVE SYSTEM RELIABILTY
1

Replacement of Obsolete 33kV I/D switchgear in 6No. Substations in Accra

S/S ‘H’, Achimota BSP

2

Supply only and supply & Installation of 33kV outdoor switchgear and equipment at Effiduase Substation

3

Supply and Installation of additional 33kV Bays at Cape Coast Bulk Supply Point and Construction of New Control Room Building Including SCADA Office

4

Construction of a 25km 2x40MVA 33kV Double Circuit Tower Line from Kumasi “D” to Kuntunase Switching Station

5

Laying of underground cables from ECG’s Airport City substation to connect the proposed Shiashie Substation

6

Laying of 2x3x2(1x630sq.mm) XLPE 33kV Al cables from the 33/11kV substation 'B' at Korle-Bu to James Town

7

Laying of 2x6(1x630sq.mm) XLPE 33kV Al cables from the Proposed Darkuman Substation to Darkuman Official Town Traffic Light

8

Conversion of the Anloga 11kV line to 33kV & linking it to the Adina 33kV line (ECG/ANLOGA-11-CONVERSION/15)

9

Relocation of Existing 11kV Underground Cables at Cape Coast BSP

10

Improvement & extension of supply to parts of Adjen Kotoku

11

Extension of supply to parts of Obeyie

12

Low Voltage Network Improvement at Fise – Amasaman (Ga West District)

13

Development of electricity supply at Ayikai Doblo

14

Extension of supply to parts Obeyie Phase II and Rehabilitation of LV network at Hebron

15

System Improvement at Afuaman

16

Extension of supply to parts of Oyibi Buade Phase II

17

Injection of 15no. 50kVA PMTs and 3no. 100kVA PMTs at Nmai Djor-Legon District

18

Extension of supply to Apirede – Akuapem Mampong (Phase II)

19

Expansion of LV network at Kyeakor

20

System Improvement at Akyawkrom and Achinakrom

21

LV supply improvement at Kofi Sarpong

22

Extension of supply to Asamang

23

Relocation Works at Circle Interchange

24

Relocation Works Agona Junction to Elubo Border

25

Relocation Works at Tarkwa- Bogoso-Ayanfuri

26

Construction of a 2X 10MVA 33/11kV Primary Substation at Asamankese and a 25km 2X 40MVA 33kV circuit

27

Construction of 2X60MVA Double Circuit Tower Line from Akyempim BSP to the Damang Mines

28

Construction of 33/11kV 2x10MVA Primary Substation at Offinso

29

Construction of a 33/11kV Outdoor Primary Substation at Barekese

30

Construction of 2 x 60MVA 33kV Double Circuits Line between Takoradi Substation “C” and Western Diamond Cement Factory

31 Laying of 2x3x2(1x630sq.mm) XLPE 33kV Al cables from the 33/11kV Substation 'B' at Korle-Bu to James Town
32

Construction of an 8.5cct-km Double Circuit tower line from Tokuse S/S to the Kasoa Switching Station

33

Network Extension Projects in the Central and Western Regions – CB Electric Phase I

34

Relocation Works at Eastern Corridor    

35

Relocation Works at Teshie Link Road

36

Network Extension Projects in Eastern and Volta regions – CB Electric Phase II

37

Reconductoring and reinsulation of 11kV networks in forested areas within Somanya District

38 Replacement of weak concrete/wooden poles with steel tubular poles on HV network from Winneba to Swedru, Central region
39 Replacement of wooden poles with steel tubular poles on bush fire prone sections of the 33kV Nkwanta feeder
40

Reinsulation of Benso/Bobikuma 33kV Feeder in Central Region

 

 

 

energysavin4.jpg
Announcement

Careers

 

Connect With Us

Head Office
Electro Volta House
P.O. Box 521, Accra
Tel: +233 (0)302 676727-47
Fax: +233 (0)302 666262
Call Center: +233 (0)302 611611
Email: ecgho@ecggh.com

Social Media